A full timber frame shell for a new house: engineered floor joists, panel walls, gable spandrels and a trussed roof with dormer openings, all cut and raised on site. Sixteen photos, in the order it happened.
16 photos · July 2020 · every step shown
With the ground floor panels up, the engineered metal web joists went in over the top: strapped, blocked and squared off, with the openings for the stairwell formed as we went. The webs leave clear runs for services later, which saves the plumber and electrician drilling through solid timber.








Five days later the roof was going on. The saw bench lived on the green next to the plot, timber stacked and cut to order, and the trusses went up with the dormer openings framed in as part of the structure rather than cut in afterwards.




Two days after that the whole roof structure was complete: ridge, dormers and all, plumb and ready for the roofers. From first joist to framed roofline in the same week, which is the point of building in timber frame.




Send us a photo or two on WhatsApp and we will tell you straight what it needs and what it costs.